Phase 1
Phase 1 involved reconstruction and shot-concreting of the irrigation ditch lining along Reservoir #1. The irrigation lining was concreted, inlet reconstructed, and completed in 2023.
Phase 2
Phase 2 construction involves the concrete lining and tower rebuild within the reservoir.
1/23/2024 |
The project was awarded. |
2/20/2024 |
Demolition begun. |
2/28/2024 |
Demolition of concrete liner completed |
3/20/2024 |
Dirt work, shaping, and elevation marking underway |
4/4/2024 |
Lining and base prep underway. |
5/2/2024 |
Dirt work and ramp construction underway. |
➠ Read More...