Reservoir 1

Phase 1

Phase 1 involved reconstruction and shot-concreting of the irrigation ditch lining along Reservoir #1. The irrigation lining was concreted, inlet reconstructed, and completed in 2023.

Phase 2

Phase 2 construction involves the concrete lining and tower rebuild within the reservoir.
1/23/2024 The project was awarded.
2/20/2024 Demolition begun.
2/28/2024 Demolition of concrete liner completed
3/20/2024 Dirt work, shaping, and elevation marking underway
4/4/2024 Lining and base prep underway.
5/2/2024 Dirt work and ramp construction underway.
➠ Read More...


Last Updated 4/15/2024
Dirt work
Continued dirt work and ramp construction.
Dirt work
Interior maintenance ramp under construction.

Dirt work
Lining and base prep underway.

Dirt work
Dirt work, shaping, and elevation marking underway.

Demolition 2024-02-28
Completed removal of concrete liner.

Demolition 2024-02-20
Starting removal of concrete liner.

Reservoir 1
Aerial view prior to construction.