Ancient Trails Solar Field

The City of Aztec is seeking to construct a second solar field for the purpose of generating electricity.

Phase 1. Land Acquisition

  • • Completed in 2022.


  • Phase 2. Road Access

    The existing access road to the solar field requires design and improvements.
  • • Seeking quotes for materials and construction.


  • Phase 3. Design and Construction

  • • Final Design completed.
  • • Feasibility study completed; Interconnection study completed; Facilities study underway.
  • • Formal engineering of the solar field will be required.
  • • Funding is being sought. PACE application, state application, and federal applications have been submitted.



  • Last Updated 5/2/2024
    Solar Field